Storage

Large size stone sheets are packed in wood crate or pallet, use forklift to unload to the ground. 

Products need to be laid flat and stacked neatly in a dry indoor area, do not place heavy or sharp objects on top of the product. 

—

Carrying&handling

Check the stock, photograph feedback for wrong profile or damaged product. 

When moving large size sheets out of wood crate, at least two people are required to carry the sheets from both sides. Do not carry more than two sheets at a time. Avoid dragging the sheets across the site, as this may damage the edges and corners.

—

 Substrate treatment

New wall cladding: ensure surface is clean, structurally sound, dry, smooth, and free of loose paint. 

Installation over existing surface: 

Old surface of ceramic tile, stone wall, mosaics: remove hollow, cracked, loose, and peeling areas, level with cement mortar, then apply primer before cladding.

Old surface of renders and paint: remove loose, hollow, and pulverised areas, level with cement mortar before cladding.

Old surface of wallpaper: remove the original wallpaper, repair and level the substrate, apply primer before cladding.

Old surface of concrete and bricks: level with cement mortar before cladding. 

—

Adhesives preparation

Regular tile adhesive for most interior wall installation. 

Two-component waterproof high-strength epoxy adhesive recommended for wet areas, bathrooms, steel, glass, or existing tiles

—

Cutting

Use suitable tools such as circular saw to cut the stone sheet

—

Installation

1, Position with a laser or snap line marker for accuracy

2, Apply adhesive and spread evenly

3, Press stone sheet to the wall

4, Compacting by clapping

5, Masking tap

6, Grout

7, Removing masking tap

8, Clean surface